Two bays craned industrial hall
2011. March
Procurer : DKG-EAST Zrt. - http://dkgeast.hu
Our company got a commission to perform the static control of the designed foundation structures. The original planned solution wasn’t practicable because of the high subsoil water and high costs. So we worked out in details of a new foundation. These were pile foundations with CFA piles. The connections were shaped with PEIKKO anchors between the reinforced concrete columns and pile foundation. These connections were needed since the high subsoil water hindered application of the sleeve.
Services :
- Static expertise
- Structural design